不确定环境下的分布式多项目多技能资源调度策略

    Research on Scheduling Strategies of Decentralized Multi-project Multi-skilled Resource Under Uncertainties

    • 摘要: 针对资源供给不确定环境下,分布式多项目调度中全局资源冲突频发、资源扰动事件应对困难的问题,研究了多技能资源在缓解全局资源冲突、应对资源供给扰动事件中的作用。以高层管理者与子项目负责人构成的分布式决策结构为背景,构建了考虑多类多技能全局资源的优化模型,全局调度模型以最小化多项目延期成本为目标进行全局资源的技能指派与项目指派,局部调度模型以最小化子项目完工时间为目标进行任务调度。利用马尔可夫链模拟全局资源可用状态的演化,设计了多阶段随机调度策略,并提出资源外部排序和内部排序两种多技能资源调度优先规则。基于随机生成的多项目算例集进行实验分析,验证了所建模型的合理性和算法的有效性,表明多技能资源能够有效减少多项目成本与延期、缓解资源供给不确定性带来的负面影响,可为企业多项目资源调度决策提供参考。

       

      Abstract: Aiming at the frequent global resource conflicts and difficulties in responding to resource disruption events in decentralized multi-project scheduling under uncertain resource supply environments, this paper investigates the role of multi-skilled resources in mitigating global resource conflicts and coping with resource supply disruptions. Against the background of a decentralized decision-making structure consisting of senior managers and subproject leaders, an optimization model considering multiple types of global multi-skilled resources is constructed. The global scheduling model performs skill assignment and project assignment of global resources with the objective of minimizing multi-project tardiness cost, while the local scheduling model carries out task scheduling to minimize the subproject completion time. The Markov chain is adopted to simulate the evolution of the availability state of global resources, a multi-stage stochastic scheduling strategy is designed, and two priority rules for multi-skilled resource scheduling including external resource sequencing and internal resource sequencing are proposed. Experimental analysis is conducted on randomly generated multi-project instance sets to verify the rationality of the constructed model and the effectiveness of the algorithm. The results demonstrate that multi-skilled resources can effectively reduce multi-project costs and project tardiness, and alleviate the negative impacts brought by the uncertainty of resource supply. This research can provide references for enterprises’ multi-project resource scheduling decisions.

       

    /

    返回文章
    返回